  THE CONSTRUCTION WORKS ON THE EXTENSION OF APRON
ON SARAJEVO INTERNATIONAL AIRPORT

The construction works on the extension of apron on Sarajevo International Airport will be carried out in the period from July 2022 till December 2022.

Location of the construction site is on east side of the existing apron, as depicted in graphic portrayal of construction site of this AIP SUP.

Construction site area will be protected by a fence and inside of it there will be movements of mechanization and workers.

Information regarding the closure of taxiway A, and portion of apron (parking position number 1) on the apron due to construction works, as well as any other changes regrading the planned construction works limitation of operation for maximum aircraft code C), will be issued by NOTAM.

Figure 1.  The first phase of works (25.5 m from the edge of TWY)
Figure 2.  The first phase of works (18 m from the edge of TWY)
Figure 3.  The second phase of works (parking position 1)
Figure 4.  The third phase of works (period of closing TWY)